Scheduling of packages
A package’s schedule controls when the agent may run the package on the units it’s assigned to.
Open the schedule
Section titled “Open the schedule”- In Configuration Management, right-click the package and select Scheduling….
- Select or clear Enabled to turn the schedule on or off.
- Set the schedule on the Start, Interval and Recurrence tabs, as described in the following sections.
- Click OK.
If you select several packages in the content view, Scheduling opens a submenu with Modify schedule, Disable schedule and Enable schedule. Modify schedule applies the schedule you set to all the selected packages.
Set when the schedule is active
Section titled “Set when the schedule is active”On the Start tab:
- Under Activate Schedule, select the date and time the schedule takes effect.
- Under Deactivate Schedule, select No end date, or select End by and a date and time when the schedule expires.
Set an interval
Section titled “Set an interval”An interval limits the period of each day in which the schedule is active. The interval is 24-hour based, so the period can run past midnight.
On the Interval tab:
- In Begin and End, enter the start time and the end time of the period in which the package is allowed to run.
- Optionally, enter a Duration instead of an end time. The other values adjust automatically.
Set a recurrence
Section titled “Set a recurrence”A recurrence defines how often the package runs.
On the Recurrence tab, select one of these options:
- Once: the package runs once. This is typical for installing a software package.
- Periodical: the package runs Daily, Weekly or Monthly. For Daily, enter the number of days between runs in Recur every. Hourly isn’t available for packages.
- Always: the package runs every time the agent runs. This is typically used to keep critical inventory information updated.
Optionally, select End after and enter the number of occurrences after which the package stops running.